Production and logistics: how the pieces are held together

Technical data in order, data capture on the shop floor, finite-capacity planning and a traced warehouse: the sequence that makes times and costs reliable.

Manufacturers need two pieces of information that the management system alone often does not give: when an order will be ready and how much it really cost. The first requires planning that takes real capacity constraints into account; the second requires capturing the data where the work happens, on the shop floor.

That is why we add two specialist tools to the management system, each with its own page: Cyberplan, the APS by Cybertec for which we are a VAR, for finite-capacity scheduling, and PROMAN MES for production progress and machine connectivity.

This page explains how they are held together: the loop closes when the plan takes account of the reality of the shop floor, the shop floor declares progress, the management system records consumption and costs, and management sees the variances on a dashboard.

The elements of the production system

APS scheduling

With Cyberplan: finite-capacity plans that consider machines, set-ups, shifts and materials, with “what if” simulations.

Shop-floor MES

With PROMAN: declaration of operations from a terminal or tablet, cycle times, machine downtime, scrap and reason codes.

Industry 4.0 connectivity

Automatic acquisition of data from the machines and sending of work instructions where technically provided for.

Logistics and warehouse

Guided picking, receipts, locations, batches and serial numbers with radio-frequency terminals.

Industrial costing

Comparison between planned and actual costs by item, operation and job order, with variance analysis.

Shop-floor documentation

Drawings, instructions and routings available at the station, always in the correct version.

APS scheduling

Planning with the real constraints, not with infinite capacity

A traditional MRP assumes the work centres are always available. An APS such as Cyberplan — for which we are value-added resellers — reasons differently: it starts from the actual capacity, the set-ups, the shifts and the materials available and builds an executable plan.

  • Delivery dates calculated on real constraints, to be given to the customer without invented safety margins.
  • Simulations: what happens if I bring this job forward or if a machine stops.
  • Sequences optimised to reduce set-up times.
  • Visibility on the bottlenecks, with loads by work centre.

Honest prerequisites

An APS returns useful plans only if the basic data is in order. Before installing anything we check together:

  • bills of materials that are up to date and consistent with what is produced;
  • routings with realistic times, not copied ones;
  • master data for work centres and shifts;
  • reliable purchasing lead times.

Logistics and warehouse

The right materials, in the right place, recorded straight away

With locations, radio-frequency terminals and guided picking the warehouse stops being the place where data gets lost.

Guided picking

The operator follows the routes and quantities indicated by the system, with confirmation by barcode scan.

Batches and traceability

Batches, serial numbers and expiry dates traced on the way in and the way out, for supply-chain traceability and recalls.

Stocktaking

Cycle counts without stopping the warehouse, with differences analysed by cause.

Go-live

How we bring manufacturing into the company

In production the order of the steps is everything: first the basic data, then data capture, and finally advanced planning. Skipping the first step is the fastest way to lose confidence in the system.

  1. Checking the basic dataBills of materials, routings, work centres and times: cleansed and aligned with what actually happens.
  2. Shop-floor data captureStations, terminals and reason codes defined with the department heads; start on a pilot line.
  3. Machine connectivityWhere provided for, automatic acquisition of counts, times and downtime from the equipment.
  4. SchedulingIntroduction of the APS once the data is reliable, comparing plan and actuals.
  5. DashboardsShop-floor and management indicators: punctuality, efficiency, scrap, cost by job order.

Would you like delivery dates you can trust?

We start with a check of your existing production data and indicate the shortest route to get there.